170
社区成员




Which course does this assignment belong to | EE301 |
Where are the requirements for this assignment? | Teamwork—beta Spring |
Team Name |
FUZHUAN |
The objective of this assignment | Day 3-4 — SCRUM and PM Report |
Other Reference Documents | Method of Construction ( 《构建之法》) |
目录
Team Member | Accomplishments | Time Spent | Remaining Tasks | Issues/Problems | Plan for Tomorrow |
---|---|---|---|---|---|
Zhang Yuxin | Developed secondary features, including user settings and product categorization. | 6 hours | Complete final API integrations. | Issues with API response format. | Finish API integration and test functionality. |
Luo Yuxin | Fixed minor frontend issues and began implementing user feedback. | 5 hours | Implement remaining frontend features. | Compatibility issues with different devices. | Work on device responsiveness and finalize user flows. |
Yang Ruoxin | Completed user interface for product details and feedback section. | 5 hours | Add filters to search functionality. | UI components breaking on certain pages. | Fix UI bugs and ensure proper page transitions. |
Lin Jiahui | Implemented product listing features and adjusted product view page. | 6 hours | Finalize user purchase flow. | Data display issues on product pages. | Debug and optimize product listing pages. |
Sun Xing | Completed API integration for product data management. | 5 hours | Test integration with the frontend. | Minor bugs with product data retrieval. | Conduct frontend testing to resolve bugs and ensure smooth flow. |
Chen Yike | Fixed database schema issues and improved performance for product listing. | 5 hours | Implement advanced search query optimizations. | Slow database queries on large data sets. | Optimize database queries for faster performance. |
Task | Estimated Time | Issues Count |
---|---|---|
Secondary feature development | 16 hours | 4 |
Frontend integration with feedback | 10 hours | 3 |
API optimization and testing | 8 hours | 2 |
Task | Time Spent | Issues Completed |
---|---|---|
Secondary feature development | 14 hours | 3 |
Frontend integration with feedback | 9 hours | 2 |
API optimization and testing | 6 hours | 2 |
Task | Remaining Time | Remaining Issues |
---|---|---|
Secondary feature development | 2 hours | 1 |
Frontend integration with feedback | 1 hour | 1 |
API optimization and testing | 2 hours | 1 |
The volume of bugs and issues increased during the testing phase due to unexpected UI compatibility issues across different devices. We also encountered several problems with API responses that required additional time for debugging.