CodeStrike Alpha Sprint Essay 2 — Day 3–4 (November 23–24, 2026)

Basic Information

ItemInformation
CourseEE308FZ Software Engineering
AssignmentAssignment 5 — Alpha Sprint
TeamCodeStrike (Group 5)
ProjectCampus Competition & Activity Community (竞伴校园)
Sprint PeriodNovember 21–28, 2026
Reporting PeriodNovember 23–24, 2026
GitHub RepositoryCodeStrike Repository
Integration Branchsprint/alpha
Main Sprint TaskT4 — Competitions & Teams Integration
Task StatusCompleted

Table of Contents

  1. Sprint Overview
  2. Daily Development Progress
  3. Core Feature Implementation
  4. Latest Running Screenshots
  5. GitHub Task and Commit Evidence
  6. Sprint Burn-up Chart
  7. Testing and Quality Assurance
  8. Problems Encountered and Solutions
  9. Next Sprint Plan
  10. Sprint Reflection

1. Sprint Overview

The second reporting period of the CodeStrike Alpha Sprint focused on T4 — Competitions & Teams Integration, following the schedule established in the published sprint plan.

During the first reporting period, the project completed baseline integration, shared HTTP communication, and MySQL-backed authentication and profile management.

Building on this foundation, T4 connected the application's central business workflow to the real FastAPI backend and MySQL database, covering competition discovery, team creation, recruitment publication, student applications, and captain decisions.

Particular attention was given to team capacity, recruitment visibility, application integrity, and access control.

By November 24, T4 had completed implementation, automated verification, pull request integration, and formal task acceptance.

2. Daily Development Progress

2.1 Day 3 — November 23: Implementation and Business Integration

Development began with a comparison between the backend OpenAPI specification and the existing frontend prototype view models.

The identified contract differences were documented before implementation. Shared DTOs and explicit adapters were subsequently extended to support the actual competition and team APIs.

The main development activities included:

  • Connecting eight existing frontend pages to real backend services.
  • Integrating competition discovery and server-side search.
  • Implementing team creation and recruitment revision workflows.
  • Connecting application submission, withdrawal, history, and captain decisions.
  • Correcting two backend response inconsistencies.
  • Expanding automated API, database, and browser verification.

The implementation introduced 11 API route contract tests and 29 competition and team end-to-end tests.

The production H5 application was also tested against the running backend, completing 53 browser assertions and capturing eight functional screenshots.

The principal implementation commit was 8f84d65.

2.2 Day 4 — November 24: Verification and Integration

The existing test suites and T4 verification procedures were executed again before final integration.

The backend tests, frontend tests, database checks, application builds, and H5 browser verification produced consistent passing results.

Pull Request #12 was merged into sprint/alpha at 09:21:13 Beijing time.

Following the recorded verification and acceptance results, Issue #4 was closed at 09:23:03.

The sprint evidence index and burn-up chart were subsequently updated to reflect the actual completion date.

3. Core Feature Implementation

3.1 Competition Discovery

The competition list and detail pages now retrieve data from the real FastAPI backend.

Competition-name search is performed through the server-side query parameter. Registration status, deadline information, and associated recruitment records are retrieved from the backend.

The implementation preserves the existing loading, empty, and error states while preventing unpublished competitions from appearing in public listings.

3.2 Team Creation and Recruitment

Authenticated students can create teams using the real POST /teams endpoint.

Selected skills are mapped to identifiers from the backend skill catalog rather than being submitted as mock skill names.

The backend validates profile completeness, competition eligibility, and team capacity. The captain is counted as the first active member of the team.

Recruitment publication follows a controlled workflow:

Team creation → Recruitment revision → Administrator approval → Public recruitment

Unapproved recruitment records remain unavailable to public users. The Open/Closed recruitment switch and Delisted visibility restrictions are enforced by the backend.

During T4 verification, administrator approval was performed through the existing authorized moderation API. The complete administrator interface remains within the scope of T6.

3.3 Application Submission and History

Students can submit applications, withdraw eligible applications, and retrieve their application history through authenticated API requests.

The backend prevents duplicate Pending applications for the same student and team.

Students with incomplete profiles are required to complete their information before applying. Skill mismatch is treated as advisory rather than an automatic rejection.

Approved, Rejected, and Withdrawn application records are retained in the database, supporting persistent application history.

3.4 Captain Review and Membership

Captains can retrieve Pending applications for their own teams and approve or reject applicants.

The frontend converts decision actions into the backend's expected Approved and Rejected values.

A successful approval creates an active membership record. Rejection preserves the application history without creating membership.

Unauthorized users cannot access another team's review queue or perform captain decisions.

The prototype Persona Switcher is disabled in API mode, ensuring that actual permissions depend on authenticated server-side identities.

3.5 Capacity and Privacy Protection

Team capacity and privacy restrictions are enforced by the backend rather than relying solely on frontend controls.

A concurrent last-slot approval test was performed using MySQL 8.4.6. Two simultaneous approval requests competed for one remaining position, and exactly one succeeded. The other was rejected with TEAM_FULL.

The team remained within its permitted capacity.

Privacy verification confirmed that applicant previews exclude private contact details. Protected member contact information is accessible only to the authorized captain of the corresponding team.

Ordinary members and non-members cannot retrieve such information through the protected endpoint.

4. Latest Running Screenshots

The following screenshots were captured from the production H5 build in API mode at a 390 px viewport, connected to the real FastAPI backend and MySQL database.

4.1 Competition Discovery

img

Figure 1. Competition Discovery Using Real Backend Data

The competition list displays backend-provided competition information after a server-side search, demonstrating the transition from mock data to actual API integration.

4.2 Team Creation

img

Figure 2. Team Creation Form with Backend Skill Catalog

The team creation form uses available competition information and the real skill catalog. Team capacity and profile eligibility are validated by the backend when the request is submitted.

4.3 Recruitment Publication

img

Figure 3. Published Team Recruitment

Following administrator approval, the recruitment becomes publicly visible within the corresponding competition.

4.4 Application Submission

img

Figure 4. Recruitment Detail After Application Submission

An authenticated student submits an application through the real backend. The resulting application state is persisted in MySQL and retrieved by the frontend.

4.5 Captain Review

img

Figure 5. Captain Review of Pending Applications

The captain review interface displays eligible Pending applications, applicant profile previews, and skill-match information while excluding private contact details.

4.6 Membership Confirmation

img

Figure 6. Team Membership After Successful Admission

After the application is approved, the updated team membership is retrieved from the backend. Database-level verification confirms that the membership record has been persisted.

5. GitHub Task and Commit Evidence

T4 was implemented on a dedicated feature branch and integrated into sprint/alpha through a pull request.

ItemEvidence
Sprint TaskT4 — Competitions & Teams Integration
PriorityP0
GitHub IssueIssue #4
Development Branchfeat/4-competitions-teams
Implementation Commit8f84d65
Pull RequestPR #12
Merge Commite05d333
Merge DateNovember 24, 2026
Issue StatusClosed

The task acceptance record includes implementation details, verification results, and the associated evidence directory.

The repository maintains the established feature-branch workflow without modifying the stable main branch or the historical Assignment 4 prototype branch.

Detailed records are available through the T4 Delivery Record.

6. Sprint Burn-up Chart

img

Figure 7. CodeStrike Alpha Sprint Burn-up Chart — Day 3–4

The burn-up chart measures the cumulative number of accepted tasks against the nine tasks established in the published sprint plan.

DateTotal ScopeAccepted Tasks
November 2190
November 2293
November 2393
November 2494

T1, T2, and T3 were accepted during the first reporting period.

Although T4 implementation and local verification were completed on November 23, the task was not counted as accepted until its pull request was merged and Issue #4 was closed on November 24.

The cumulative completion count is now four out of nine planned tasks, representing approximately 44.4% by task count.

The overall sprint scope remains unchanged. The chart measures accepted tasks rather than story points or development effort.

The remaining five tasks will continue according to the published sprint schedule.

Burn-up Chart Data

7. Testing and Quality Assurance

7.1 Automated Verification Results

The T4 implementation was verified through frontend tests, backend tests, database inspection, production builds, and browser-based end-to-end testing.

VerificationResult
TypeScript type checkingPASS
Student mock and unit tests78 passed
Student end-to-end tests44 passed
Administration HTTP tests8 passed
Backend pytest on MySQL 8.4.666 passed, 0 skipped
MySQL integrity test subset5 passed
Direct database-state checks22 passed
Real H5 business workflow53 assertions passed
Actual H5 API requests101
OpenAPI contract verificationPASS
H5 production builds — Mock and APIPASS
WeChat Mini Program compilationPASS
Administration web buildPASS

The MySQL integrity tests are included in the backend test suite and are not counted as additional independent backend tests.

7.2 Business Rule Verification

Test ScenarioObserved Result
Recruitment before approvalNot publicly visible
Recruitment after approvalPublicly visible
Valid student applicationPending record created
Duplicate Pending applicationDUPLICATE_PENDING
Incomplete student profilePROFILE_INCOMPLETE
Skill mismatchApplication remains permitted
Captain approvalActive membership created
Captain rejectionRejected history retained
Approval beyond team capacityTEAM_FULL
Concurrent last-slot approvalsExactly one successful approval
Unauthorized access to contactsFORBIDDEN
Delisted recruitmentExcluded from public listings

The concurrent approval test was performed against a real MySQL 8.4.6 instance using the READ-COMMITTED isolation level.

Direct database inspection confirmed the persistence of team, membership, application, and recruitment revision records.

7.3 Regression and Verification Boundaries

Existing Assignment 4 prototype functionality was preserved. The three prototype regression suites passed 52, 232, and 227 assertions respectively.

The backend OpenAPI specification remained consistent at 58 paths and 47 schemas.

The current verification also has the following boundaries:

  • The capacity refusal was verified through client responses and database state, but its rendered error banner was not captured.
  • The administrator approval step was tested through the authorized API; the full administrator interface belongs to T6.
  • The WeChat Mini Program compiled successfully, but its operation in WeChat Developer Tools and on physical devices has not yet been verified.
  • Continuous integration has not yet been configured in the repository.

Detailed logs and screenshots are retained in the T4 Evidence Directory.

8. Problems Encountered and Solutions

8.1 Missing Team Identifier in History Responses

Problem: The team history endpoint did not return the team identifier required by the frontend to associate historical membership records with their corresponding teams.

Solution: The backend response projection was extended to include teamId and the relevant team-state fields.

A dedicated regression test was added to verify that the returned historical record identifies the correct team.

8.2 Missing Recruitment Match Information

Problem: Public recruitment responses did not include personalized skill-match information, preventing accurate presentation of recruitment compatibility for authenticated students.

Solution: The recruitment endpoint was extended to accept optional authentication and calculate actual skill overlap for the current viewer.

Anonymous public access remains available. Regression tests verify matched, unmatched, and unusable-token cases.

8.3 Concurrent Approval and Capacity Protection

Challenge: Simultaneous approval requests could compete for the final available team position.

Verification: A real MySQL concurrency test confirmed that transaction serialization prevents both requests from occupying the same remaining position.

The successful request created the membership, while the second was rejected with TEAM_FULL. The final database state remained within the permitted team capacity.

This verification demonstrates the importance of database-level consistency in addition to frontend validation.

9. Next Sprint Plan

According to the published Alpha Sprint schedule, the next reporting period, November 25–26, will focus on T5 and T6.

TaskPlanned Development
T5 — Community Posts & InteractionsCommunity posts, comments, likes, favorites, and image upload
T6 — Admin Web IntegrationAdministrator authentication, dashboard data, competition management, and moderation

The next phase will reuse the shared HTTP infrastructure, authentication system, and verified competition and team workflows.

Preparation for WeChat Mini Program compatibility verification will also continue under T9 without replacing the established development schedule.

The remaining implementation work will follow the existing task acceptance criteria, GitHub workflow, and evidence collection standards.

10. Sprint Reflection

During the second reporting period, CodeStrike extended its database-backed account system into a functional competition and team collaboration workflow.

T4 demonstrated the integration of frontend interaction, backend authorization, recruitment moderation, application processing, and persistent membership management.

The verification of duplicate applications, concurrent approvals, capacity limits, and protected contact information was particularly important because these rules directly affect system reliability and user privacy.

With T1–T4 accepted, the project has established its principal student-side business foundation. The next phase will extend this foundation to community interaction and administration functionality while maintaining reproducible testing and traceable delivery evidence.


Related Links

...全文

相关推荐

高校技术转移中心如何选型管理系统?数智化工具如何破解成果转化三大难题?.docx

科易网基于行业知识库+行业大数据+科技资源要素+AI模型,以AI,赋能技术转移、成果转化、技术经理人培训、知识产权管理、区域产业分析与布局、地方科技招商、创新创业大赛等场景,推出科技创新领域的AI工具、场景化服务和数智化解决方案,推动科技创新与产业创新智能化发展。

BIZKEEN

iperf3 安卓版 - 手机网络测速工具(客户端/服务端/双向打流)

基于 iperf3 3.22 源码交叉编译的 Android 原生测速 App,手机可直接作为 iperf3 客户端或服务端。 功能:客户端/服务端双模式;TCP/UDP;多并发流;反向下载 -R;双向打流 --bidir;UDP 带宽按 Mbps 设置;实时速率曲线与当前/平均/峰值;历史记录;Material3 界面。 安装:下载 APK,允许未知来源安装。支持 Android 7.0+,架构 arm64-v8a / armeabi-v7a / x86_64。iperf3 遵循 BSD-3-Clause 协议,版权归 ESnet。

 吖吖伊

生产制造企业智慧工厂MES一体化管理平台解决方案.pptx

生产制造企业智慧工厂MES一体化管理平台解决方案.pptx

公众号:优享智库

考虑分布式电源运行特性的有源配电网智能软开关SOP规划方法【IEEE33节点】(Matlab代码实现)

内容概要:本文研究了考虑分布式电源运行特性的有源配电网智能软开关(SOP)规划方法,并基于IEEE33节点系统进行了Matlab代码实现。该方法旨在通过引入SOP这一先进的电力电子装置,提升配电网对分布式电源(如光伏、风电)的接纳能力与运行灵活性。研究综合考虑了分布式电源出力的波动性和不确定性,构建了以网损最小、电压偏差最小等为目标的优化模型,并采用合适的智能优化算法求解SOP的最佳安装位置和容量配置。文中详细阐述了模型构建的理论基础、关键约束条件的处理方式以及仿真算例的设置与结果分析,验证了所提方法在改善配电网电压质量、降低网络损耗和促进清洁能源消纳方面的有效性。; 适合人群:具备电力系统分析、优化算法基础,从事配电网规划、分布式能源接入等相关研究的研究生、科研人员及电力公司技术人员。; 使用场景及目标:① 掌握智能软开关(SOP)在现代有源配电网中的应用原理与规划方法;② 学习如何将分布式电源的运行特性融入配电网优化模型;③ 获取基于IEEE33节点系统的Matlab代码实现,用于复现经典算例或进行二次开发研究。; 阅读建议:此资源紧密结合理论与实践,不仅提供了详细的数学模型推导,还给出了完整的Matlab代码。读者应在理解优化模型和SOP工作原理的基础上,结合代码进行仿真调试,深入分析不同场景下SOP的配置方案对配电网性能的改善效果。

茜姐_博客

技术转移机构想要获得官方认可,需要满足哪些资质认定标准?.docx

技术转移机构想要获得官方认可,需要满足哪些资质认定标准?

BIZKEEN
评论 1
收藏 已收藏
分享
返回顶部