分享| The Link Your Class | https://bbs.csdn.net/forums/MUEE308FZU202201 |
| The Link of Requirement of This Assignment | https://bbs.csdn.net/topics/610142480 |
| TeamName | Group 2 _ 一站式开源硬件交流社区——ELECO(电子) |
| The Aim of This Assignment | Summarize the previous work of the team & Develop an Alpha sprint plan |
Contents
Part 1 Teamwork Summary Reflections
1.1 Summarize the previous work of the team
1.2 Record the defense Opinions & Quesitons
Part 2 Sprint team division of labor
Part 3 Team project's GitHub repository

In the previous work, we initially decided on our future project, conducted user and industry requirements analysis and market research for our project and wrote a project requirements document, defined the project's functionality in detail, and drew a product prototype and UML diagram for the project.
During the opening defense on Saturday, we were asked two questions:
Over the next two weeks, we will use APIFOX and the Integrated Development Environment to do the following:
TABLE 1 Alpha sprint plan
| Time | Front End | Back End | Test |
| 12.5~12.6 | Implement user registration and login functions | Implementation of user registration and login ports setting | Debug user registration, login interface, search for recognition hardware images |
| 12.7~12.8 | Implementing user page interaction functions |
Inject virtual post data to achieve user post pulling and following functions. Train hardware recognition dataset | Debug the post pull function module. Assist in training hardware recognition dataset |
| 12.9~12.10 | Implement sub-section function and search function | Implement post database addition, deletion and development of post file upload function | Test file upload interface and posting feasibility |
| 12.11~12.12 | Implement posting function | Implement post editing and publishing functions | Test the post publishing page |
| 12.13~12.14 | Implement inter-page jumping function and hardware recognition function | Implementation of hardware recognition interface | Test hardware identification module |
| 12.15~12.16 | Final project commissioning | Final project commissioning | Fianl project testing, focusing on hardware identification and posting functions |
TABLE 2 Division of labor
| Assignment of work | Responsible person |
|---|---|
| Front-end | She Zixiang, Zheng Zheyi |
| Back-end | Zhao Rui, Chen Kaifeng, Zhu Liao |
| Test | Lin Mingrui, Ou Zhenhui, Wang Enyi |
| UI Design | Xu Xin, Wang Weiqin |
| Blog, Vlog, PPT | Lin Mingrui,Ou Zhenhui, Xu Xin, Wang Wei |
Front-end:https://github.com/JeacsonSnake/SE_OSHC